==Pilot Details== |
==Pilot Details== |
||
Nepal's Department of Education is planning to pilot OLPC at a test school in April of 2008. Nepal's Minister of Education, Pradip Nepal, strongly support the OLPC program. Currently, the pilot is planned at a Kathmandu-area school. The Danish IT Society has generously donated roughly 200 XO laptops for the pilot. |
Nepal's Department of Education is planning to pilot OLPC at a test school in April of 2008. Nepal's Minister of Education, Pradip Nepal, strongly support the OLPC program. Currently, the pilot is planned at a Kathmandu-area school. The Danish IT Society has generously donated roughly 200 XO laptops for the pilot. |
||
Line 5: | Line 7: | ||
[http://www.olenepal.org OLE Nepal] is coordinating many aspects of pilot including teacher training, learning activity development, networking, and hardware deployment. |
[http://www.olenepal.org OLE Nepal] is coordinating many aspects of pilot including teacher training, learning activity development, networking, and hardware deployment. |
||
==[[Nepal:Testing Plans|Testing Plans]]== |
|||
* Hardware |
|||
* Activities |
|||
* Networking |
|||
* Power |
|||
==Team Members== |
==Team Members== |
||
Line 20: | Line 16: | ||
From [http://www.olenepal.org OLE Nepal] |
From [http://www.olenepal.org OLE Nepal] |
||
* Rabi Karmacharya, Project Lead |
|||
* Dr. Saurav Dev Bhatta, Teacher training and curriculum development for the pilot |
* Dr. Saurav Dev Bhatta, Teacher training and curriculum development for the pilot |
||
* Bryan Berry, lead systems engineer |
* Bryan Berry, lead systems engineer |
||
Line 29: | Line 26: | ||
* [http://www.olpcnepal.org OLPC Nepal] Localization and activity development |
* [http://www.olpcnepal.org OLPC Nepal] Localization and activity development |
||
Other volunteers: |
|||
⚫ | |||
* Tony Pearson, software engineer |
|||
⚫ | |||
==Timeline== |
==Timeline== |
||
Feb 5th - Submit use cases and Requirements |
|||
The Nepali government still hasn't selected the pilot school. We will shift much of the testing to the school premises once it is selected. |
|||
=== Week 1 Feb 11 - 15 === |
|||
Build out basic features of test School Server and several test XO's |
|||
=== Week 2 - Feb 17 - 22 === |
|||
Comprehensively test Deployment Build 1 for the School Server together w/ XO's |
|||
The Deployment Build for the server is simply the stock XS 150 Build plus the content we are bundling into it |
|||
See the online spreadsheet for what's included in [http://spreadsheets.google.com/pub?key=pJrekGFLbqe6sdOitu3tYbQ Deployment Build 1] |
|||
=== Week 3 - Feb 24 - 29 === |
|||
# Fix problems found Deployment Build 1 |
|||
# Stress test XO's, school server, and active antenna |
|||
# Work on automating the hardware testing process, particularly for testing XO batteries and mesh networking |
|||
=== Week 4 - March 2 - 7 === |
|||
# Work on XS Deployment build 2 for the School Server |
|||
# Testing should begin at the school site by this time |
|||
=== Week 5 - March 9 - 14 === |
|||
# Test XS Deployment Build 2 |
|||
# Set up and test a deployment build for the XO for the pilot |
|||
=== Week 6 - March 16 - 21 === |
|||
=== Week 7 - March 23 - 28 === |
|||
=== Week 8 - March 30 - April 4 === |
|||
=== Week 9 - April 6 - 11 === |
|||
=== Week 10 - April 13 - 18 === |
|||
== Important dates: == |
|||
* March 15th - Receive 50 XO's |
|||
* Early April - Receive 150 additional XO's |
|||
* April 5 or 8 -- 7 days training session for teachers |
|||
* April 10th -- National Parliamentary Elections, may delay start of school |
|||
* April 13th -- School starts |
|||
* April 13 - 15 -- In-school training for kids and teachers |
|||
==Teacher Training Plan== |
|||
* The training will be for a total of 7 days. |
|||
* The first 4 days of the training will be residential (i.e., in a hotel/motel away from the school)--could be from April 5 to 8 |
|||
* The teachers will go home after that. And there will be a few days gap before the start of the school year. |
|||
* During this gap, the elections will be held. Plus the teachers will have a couple of days of formal interactions with parents and other stakeholders in the school itself where they will not only introduce the participants |
|||
== [[Nepal:Redundancy|Strategy for Redundancy]] == |
|||
[[category:Nepal]] |
|||
[[Category:OLPC Nepal]] |
Latest revision as of 13:56, 2 May 2008
This page is totally out of date and I need to clean it up. My apologies Berrybw 06:40, 13 March 2008 (EDT)Pilot DetailsNepal's Department of Education is planning to pilot OLPC at a test school in April of 2008. Nepal's Minister of Education, Pradip Nepal, strongly support the OLPC program. Currently, the pilot is planned at a Kathmandu-area school. The Danish IT Society has generously donated roughly 200 XO laptops for the pilot. 50 laptops should arrive in Mid-March and the remainder will arrive early April. The pilot will take place at a single school in the outskirts of Kathmandu. Laptops will be piloted in grades 2 and 6 (ages 6 and 11). OLE Nepal is coordinating many aspects of pilot including teacher training, learning activity development, networking, and hardware deployment. Team MembersFrom the Department of Education:
From OLE Nepal
Other groups involved:
Other volunteers:
Personnel Needs: Need to designate someone to test and prepare the power solutions. Ram Krishna Singh would be ideal but he is very busy developing activities for the pilot. TimelineThe Nepali government still hasn't selected the pilot school. We will shift much of the testing to the school premises once it is selected.
Week 1 Feb 11 - 15Build out basic features of test School Server and several test XO's Week 2 - Feb 17 - 22Comprehensively test Deployment Build 1 for the School Server together w/ XO's The Deployment Build for the server is simply the stock XS 150 Build plus the content we are bundling into it See the online spreadsheet for what's included in Deployment Build 1
Week 3 - Feb 24 - 29
Week 4 - March 2 - 7
Week 5 - March 9 - 14
Week 6 - March 16 - 21Week 7 - March 23 - 28Week 8 - March 30 - April 4Week 9 - April 6 - 11Week 10 - April 13 - 18Important dates:
Teacher Training Plan
Strategy for Redundancy |