8.2.1 Planning and process page - Take 1 by [[User:Gregorio|Gregorio]] 21:03, 2 October 2008 (UTC)
== Release planning ==
Take 3 [[User:Gregorio|Gregorio]] 20:31, 24 December 2008 (UTC)


This release is targeted for Uruguay but it wil be available to everyone and probably will be used in manufacturing. It is a maintenance release based on [[8.2.0]]. As such it does not contain the latest changes and the goal is to minimize changes in order to bound the test cycle.
= Objective =
Ensure smooth deployment for countries rolling out or upgrading between December and April.


== Standard information ==
The date and target bug fix set will be determined by the lead customers. The next steps are to listen to the customers and the bug fixes they need. Then can scope the fixes and pick a target release date.


<small>These are all semantic annotations that other pages such as [[Releases]] can query.</small>
= Date =
Must be posted by November 15. Any later and Rwanda will miss their opportunity to upgrade.<br>
(We need to check if this is still the case and monitor how their deployment is going. We can have a similar problem as we have with Peru and Ethiopia... that we don't meet their timeline because either it moves or we don't have a good understanding of it. [[User:Kimquirk|Kimquirk]] 12:11, 3 October 2008 (UTC))


Release notes: [[Release notes::Release notes/{{PAGENAME}}]]
Change control must start by October 30.<br>
[[Category:Releases]]
(If we decide Nov 15th is an important date, then change control needs to start by Oct 24. And we should have a candidate release, and a signed build for testing by Oct 31. With this very short time frame, we need to think of this release as a 3 week bug fix sprint starting next week. [[User:Kimquirk|Kimquirk]] 12:11, 3 October 2008 (UTC))


Status: [[Status::released]]
Final regression test must start by November 7.


Target platforms: [[Target platforms::XO-1]]
= Target Customers =
- Peru <br>
School year starts in March but 9.1 wont be ready.


Primary maintainer: [[Primary maintainer::User:Ed McNierney]]
- Uruguay ? <br>
Check when school year starts and what it will take for them to use this release.


ECO: [[Is part of::ECO/8.2.1]]
- Rwanda <br>
School out as of October 31. Will have a window until December to upgrade


Primary objective: [[Has objective::address critical bug fixes from release 8.2.0, mostly found in Uruguay]]
- Haiti <br>
Deployment time frame on hold but should be ready by 8.2.1


Lead customer: [[Lead customer:: OLPC Uruguay]]
- Palestine <br>
Needs Arabic working


Build number: [[Build number::802]]
- G1G1 <br>
Target factory imaging as of October 1. Target delivery in December.


Download URL: Download URL: [[Download URL::http://download.laptop.org/xo-1/os/official/802/]] , also [[Download URL::http://download.laptop.org/xo-1/custom/g1g1/gg-802-1/]] with [[G1G1 2008]] activities pre-installed.
- Cambodia <br>
New keyboard support; language support


Firmware: [[Firmware::OLPC Firmware q2e41]]
- Any other target customers? Afghanistan, Mongolia, others.... <br>


Release date: [[release date::2009-05-13]]
= Rules of engagement =
We will collect the list of target bug fixes by reviewing open trac items and setting the ones we want to address to Milestone 8.2.1.


Build system: [[Build system::Pilgrim]] off [[Build platform::Fedora 9]]
Priority field will be set to High or Blocker. High bugs will be accepted until a certain date tbd. After that only blockers will be accepted.


Bug scrub decision criteria: <br>
If a bug will prevent a target customer from deploying it we will consider a high priority/blocker for the release. <br>

On G1G1 if a bug will prevent a lot of support calls we will consider it. e.g. WPA improvements may be needed. <br>

Otherwise we will consider any bugs which have a High Value and Low effort or a High Value and High Effort as long as the ROI is clear and the bug can be addressed in the target time frame.

= Major Work to Consider =
We should decide if we want to have any focus on each of these. <br>

* Power
Could be a test only effort where QA must write and execute a full set of tests.

* Collaboration
Same as power. Don't plan on major re-work but improve test capacity. Additionally consider bug fixes which are well contained?

* Lease management
Critical customer issue. Need to decide if its in or out or if there is a minimal implementation we can do.<br>
(We have been promising customers this feature for next year, 2009. As we are starting implementation, it might be important to get some pieces of the feature in for early testing, but it is not a goal to get a lease management system in place for 8.2.1. [[User:Kimquirk|Kimquirk]] 12:06, 3 October 2008 (UTC))


== Standard information ==
(These are all semantic annotations that other pages such as [[Releases]] can query.)

Release notes: [[Release notes/{{PAGENAME}}]]
[[Category:Releases]]
[[Category:Releases]]
<!-- above lines maybe could be a template -->

Status: [[status::nascent]]

Primary maintainer: [[Primary maintainer::User:CScott]]

ECO: not yet

Primary objective:
* [[Has objective::Enable deployments]]

Lead customer: [[Lead customer:: Rwanda]]<br>
(I think the lead customer might be [[Peru]], who definitely wants to be able to upgrade in Dec/Jan, and they will have over 150k laptops. [[User:Kimquirk|Kimquirk]] 12:06, 3 October 2008 (UTC))

Build number and URL: [[Build number::nnn]

Schedule: [[target date::2008-11-15]]

Latest revision as of 07:46, 6 August 2013

The contents of this page are considered outdated and some of the information may be stale. Please use information here with caution, or update it.

Release planning

Take 3 Gregorio 20:31, 24 December 2008 (UTC)

This release is targeted for Uruguay but it wil be available to everyone and probably will be used in manufacturing. It is a maintenance release based on 8.2.0. As such it does not contain the latest changes and the goal is to minimize changes in order to bound the test cycle.

Standard information

These are all semantic annotations that other pages such as Releases can query.

Release notes: Release notes::Release notes/8.2.1

Status: Status::released

Target platforms: Target platforms::XO-1

Primary maintainer: Primary maintainer::User:Ed McNierney

ECO: Is part of::ECO/8.2.1

Primary objective: Has objective::address critical bug fixes from release 8.2.0, mostly found in Uruguay

Lead customer: Lead customer:: OLPC Uruguay

Build number: Build number::802

Download URL: Download URL: Download URL::http://download.laptop.org/xo-1/os/official/802/ , also Download URL::http://download.laptop.org/xo-1/custom/g1g1/gg-802-1/ with G1G1 2008 activities pre-installed.

Firmware: Firmware::OLPC Firmware q2e41

Release date: release date::2009-05-13

Build system: Build system::Pilgrim off Build platform::Fedora 9