== Deployment Schedule ==
== Deployment Schedule ==
{| border=1 cellpadding=3
{| border=1 cellpadding=3
!Day #
!
!Date
!Projected Date
!Desired Date
!Activity
!Activity
!Owner
!Owner
Line 8: Line 9:
|-
|-
|Preparation
|Preparation
|
|
|
||Assemble team
||Assemble team
Line 13: Line 15:
||done exc. need Tech Lead
||done exc. need Tech Lead
|-
|-
|
|
|
|
|
Line 19: Line 22:
||in progress
||in progress
|-
|-
|
|
|
|
|
Line 27: Line 31:
|
|
|
|
|June ?7-16, 2010
||Initial training sessions at OLPC
||Initial training sessions at OLPC
||SB, AB, ?TM, ?JB
||
||
||
|-
|-
|
|
|
|
|
Line 37: Line 43:
||
||
|-
|-
|
|
|
|
|
Line 43: Line 50:
||
||
|-
|-
|
|
|
|
|
Line 50: Line 58:
|-
|-
|Day 0
|Day 0
|?? April 22, Thur??
|
|February 18, Thur
||Purchase order/Letter of credit issued
||Purchase order/Letter of credit issued
||
||
||
||
|-
|-
|
|
|
|
|
Line 61: Line 71:
||
||
|-
|-
|
|
|
|
|
Line 67: Line 78:
||
||
|-
|-
|
|
|
|
|
Line 73: Line 85:
||
||
|-
|-
|
|
|
|
|
Line 79: Line 92:
||
||
|-
|-
|
|
|
|
|
Line 85: Line 99:
||
||
|-
|-
|
|
|
|
|
Line 91: Line 106:
||
||
|-
|-
|
|
|
|
|
Line 98: Line 114:
|-
|-
|Day 30
|Day 30
|
|
|
||Keyboard design delivered to factory
||Keyboard design delivered to factory
Line 103: Line 120:
||
||
|-
|-
|
|
|
|
|
Line 109: Line 127:
||
||
|-
|-
|
|
|
|
|
Line 115: Line 134:
||
||
|-
|-
|
|
|
|
|
Line 122: Line 142:
|-
|-
|Day 60
|Day 60
|
|
|
||Teacher preparation begins
||Teacher preparation begins
Line 128: Line 149:
|-
|-
|Day 90
|Day 90
|
|
|
||Laptops delivered ex works
||Laptops delivered ex works
Line 133: Line 155:
||
||
|-
|-
|
|
|
|
|
Line 139: Line 162:
||
||
|-
|-
|
|
|
|
|
Line 145: Line 169:
||
||
|-
|-
|
|
|
|
|
Line 151: Line 176:
||
||
|-
|-
|
|
|
|
|
Line 159: Line 185:
|Day 120
|Day 120
|
|
|June 18, Friday
||Laptops arrive in country
||Laptops arrive in country
||
||
Line 165: Line 192:
|Day 125
|Day 125
|
|
|June 23, Wednesday
||Laptops clear customs
||Laptops clear customs
||
||
||
||
|-
|-
|
|
|
|
|
Line 175: Line 204:
||
||
|-
|-
|
|
|
|
|
Line 181: Line 211:
||
||
|-
|-
|
|
|
|
|
Line 188: Line 219:
|-
|-
|Day 135
|Day 135
|
|
|
||Regional distribution begins
||Regional distribution begins
Line 194: Line 226:
|-
|-
|Day 150
|Day 150
|
|
|
||Laptops begin arriving at schools
||Laptops begin arriving at schools
Line 199: Line 232:
||
||
|-
|-
|
|
|
|
|
Line 205: Line 239:
||
||
|-
|-
|
|
|
|
|
Line 211: Line 246:
||
||
|-
|-
|
|
|
|
|

Revision as of 06:58, 7 November 2009

Deployment Schedule

Day # Projected Date Desired Date Activity Owner Status/Next Steps
Preparation Assemble team JB done exc. need Tech Lead
Define budget JB in progress
Define any unique deployment requirements
June ?7-16, 2010 Initial training sessions at OLPC SB, AB, ?TM, ?JB
Census
Site survey
Homologation, certification process
Day 0 ?? April 22, Thur?? February 18, Thur Purchase order/Letter of credit issued
Laptops ordered
Servers, active antennae, power and connectivity equipment ordered
Localization/translation begins
Connectivity planning begins
Pedagogical planning begins
Community outreach begins
Content planning begins
Day 30 Keyboard design delivered to factory
Training manuals completed
Local technical training begins
Site preparation begins
Day 60 Teacher preparation begins
Day 90 Laptops delivered ex works
Country software “image” completed
Country content “image” completed (ebooks, etc.)
Order of activities on tool bar completed
Software QA begins
Day 120 June 18, Friday Laptops arrive in country
Day 125 June 23, Wednesday Laptops clear customs
Inventory begins (including scanning process);
Software update begins
Activation keys generated
Day 135 Regional distribution begins
Day 150 Laptops begin arriving at schools
IT infrastructure completed
Activation process performed at schools
Laptops distributed to teachers and children