Roadmap
Manu, Silke, Deepank and Mohit met on Thursday, June 26th to discuss technical issues currently being faced by the Food Force team. A number of issues were solved and the team hopes to make headway during the coming week. Deepank and Silke also developed a roadmap for the project. They hope to complete the following components of the project by the following dates.
3rd July - Artwork Deadline
7th July - View Module Completion Deadline
9th July - Storyboard Deadline
14th July - Integration of Storyboard into Game and final game.
18th July - Cutscene images inclusion and initial testing of modules.
20th July - Sugarizing of game complete
22nd July - Testing on Windows
25th July - D-Day
Buffer Time = 3 days(22-25th July)