9.1.0 requirements

From OLPC
Revision as of 10:47, 2 December 2008 by Gregorio (talk | contribs)
Jump to: navigation, search


This page defines the requirements for release 9.1.0. It is modeled after a Product Requirements Definition document which intends to define who the users are, what they need and what technology should be built in order to achieve the product and user goals.

Feature requests tracks features, requirements, and requests, and plans by customer; Feature roadmap tracks software features by technical strategy.

See also idea plans for upcoming technical conference at: XOcamp 2

Overview

This release is the first major new feature release after 8.2.0 Its is the first of two major feature releases we want to deliver in 2009. The target date for this release is March 7, 2009 (Note: date and feature set not final and subject to change).

This release must run on C1, C2, C3 and the new C4 motherboards. (check exact list and add URL)

Technical strategy

This section outlines the main areas of technology that we will focus on improving. All of the specific features should address one of these primary concerns. The choice of these comes from listening to users and deployment leads and hearing what their concerns.

The strategic priorities are focused on making the XO work the way users expect it to and helping get the XO deployed more quickly in more countries.

Greater reliability and performance

  • No loss of data. Fewer crashes and fewer open bugs than 8.2 and previous releases. See also: http://wiki.laptop.org/go/User:Gregorio/8.2.0_release_criteria
  • At the time of the release, works the way the manual says it works. That is, all of the things explained and listed in these manuals must work as described.

http://www.laptop.org/manual/

  • Better performance includes faster GUI interactions. Includes launching activities, switching from one activity to another, using the journal and using the frame. GUI, activities, back ups.

Easier to deploy and maintain

Quick, clean way to upgrade XOs in the field. Covers several cases including

  1. Creating customization images (to include language packs and rpms)
  2. Installing images in the warehouse
  3. Upgrade in the schools
  4. Updating activities
  5. Activation and Leases

Primary release drivers

Date:
The goal (not confirmed) is to release at the end of Q1 (March 2009).

Customers
Schools that will be deploying in Aug-Sept of 2009.

Features

Target deployments

See: Deployments

Standard information

(These are all semantic annotations that other pages such as Releases can query.)

Status: status::gathering requirements and setting priorities

Primary maintainer: not chosen yet

ECO: not yet

Primary objectives:

The process is not final. It is a set of rough guidelines still being worked out and subject to change.

Lead customer: ?

Build number and URL: Build number::999

Schedule: Signed and final image available for download and new XOs built with 9.1.0 in manufacturing by Target date::March 15, 2009