Future releases

From OLPC
Revision as of 12:08, 24 September 2008 by 18.85.18.112 (talk) (8.2.0 - Future)
Jump to: navigation, search


All dates and features sets on Future releases are subject to change

For past releases, see the release notes page. What release am I running?

Naming scheme

The first number in the release is its year. For example, "8.2.0" is the second significant release in 2008, and "8.1.1" is an update to the first release in 2008.

Future XO releases

See Release notes for past releases.

9.1.0 - Future

Status
Gathering requirements and setting priorities at 9.1.0
Maintainer
Not chosen yet
Primary objective
tbd
Schedule
tbd
should be first half CY 09 and possibly as early as December 2008.

8.2.1 - Future

Status
Nascent
Maintainer
Not chosen yet
Primary objective
tbd
Schedule
tbd

8.2.0 - Future

Development Details
See: 8.2.0
Join the test effort!
Draft release notes
Release notes/8.2.0
Status
Target Release Date before the end of September. This is not the final release date and subject to change.
Release candidate chosen: 8.2-763. Click the Join the test effort link above to try the release candidate.
Maintainer
Michael Stone
Primary objective
Time based release. Intended to include all the available features which are ready in time.
Lead customer
G1G1 (US first then EU and Canada), Haiti, Rwanda, Mongolia, Birmingham (?), Paraguay, Peru, Oceania
See working development page above for latest feature set, open blocking bugs and development process and status details.
Schedule
Target schedule: http://wiki.laptop.org/go/8.2.0#Schedule

8.1.3 - Future

Status
Ready, awaiting final ECO check completion and final release notes review.
Primary Maintainer
Sayamindu
Release notes
Release_notes/8.1.3
ECO
OLPC_SW-ECO_7
Primary objectives
Fix handling of Compose characters for Amharic
Lead Customer
Ethiopia
Build Name and URL
714
Schedule
Tentative release on 9/30/2008

Future XS Releases

See XS Release Notes for past releases.

XS v164

Status
 ?
Primary Maintainer
Martin
Release notes
 ?
ECO Link
 ?
Primary objective
 ?
Lead Customer
 ?
Build Name and URL
 ?
Schedule
 ?

XS v163

Status
 ?
Primary Maintainer
Martin
Release notes
 ?
ECO Link
 ?
Primary objective
 ?
Lead Customer
 ?
Build Name and URL
 ?
Schedule
 ?

Future release summary information

Experimental new format for releases page below

This is a semantic query on releases whose status is not "released". All dates and other information is tentative and subject to change! Click the release for more information. {{#ask: Status::!released

 |mainlabel=Release
 |?Status
 |?Target date
 |?Primary maintainer
 |?Is part of=ECO
 |?Lead customer=Lead customer(s)
 |?Has objective=Primary objectives
 |default=No releases with status "not released" found?!

}}

Timeline

This draggable query should show releases with a Property:Release date and/or Property:Target date. (Some future releases have neither so don't show up.) All dates and features sets on Future releases are subject to change {{#ask:

 |?Release date
 |?Target date
 |?Status
 |format=eventline

}}