(New page: {{Test case |testcase_name=50 XO, 1 AP collaboration |testcase_category=Network |testcase_subcategory=50XO |testcase_stream=Any |testcase_objective=To verify collaboration working with a 5...) |
No edit summary |
(One intermediate revision by the same user not shown) | |
(No difference)
|
Latest revision as of 22:12, 9 October 2008
Stream | ,|x|Build stream::x}} | ||
---|---|---|---|
Category | Test category::Network | Sub-category | Test subcategory::50XO |
Component | System component:: | ||
Feature | System feature:: | ||
Objective | Test objective::To verify collaboration working with a 50 XO, 1 AP testbed. | ||
Tools | Test tools::50 XOs connected to 1 AP. | ||
Setup | [[Test setup::# Connect all 50 XOs to the AP.
| ||
Procedure | [[Test procedure::# Verify (by taking a picture, sending a Chat message, and sharing a bookmark in one of the XOs) that there is connectivity and collaboration between all XOs in those 3 Activities.
| ||
Expected Results and Pass Criteria |
Pass criteria::Collaboration for all 4 activities should persist for longer than 2 hours. | ||
Comments | More notes:: |