User:Mstone/Commentaries/Releases 3
We make changes to our software for many reasons; however, we make scheduled (major) releases in order to deliver significant changes to our downstream clients. Major releases may include interface-breaking changes. They are different from unscheduled (minor) releases in that they contain larger and more thoroughly planned changes.
Process Overview
- OBJECTIVES: Choose a target month. Solicit goals and priorities for the release. Propose ends and means.
- DEVELOPMENT: Generate changes which may help to meet the new goals.
- INTEGRATION: Generate and execute a release contract for each desired change.
- RELEASE: Execute the Software ECO process to deliver the release.
Process Step Details
OBJECTIVES
Write an Objectives page (e.g. 8.2.0) recording a consensus on:
- target month.
- development goals and priorities.
- lead customers.
- feasibility of proposed changes.
Module maintainers, product management, and the release team will be responsible for building and maintaining this consensus based on communal, customer, and institutional feedback. All three groups will be responsible for acting to achieve its mandates, e.g. as advisers, maintainers, and managers.
Schedule
We have learned that certain minimum amounts of time must be allocated to integration and testing. The following example schedule records some of this knowledge:
- >90 days before target date Steam. Changes can be proposed at will and should be proposed as early as possible.
- 60 days before target date Water. Proposals must pass muster with the release team. Release contracts should be written and integration should occur. This is feature-level change control.
- 30 days before target date Ice. We branch for release and the release team produces release candidates as needed under package-level change-control. Developers should be focused on fixing bugs.
- <15 days before target date Final Test. Get consensus from test, QA, and engineering communities, then finish the Release Process Checklist.
- Release day. Announcement Day. Once Release checklist is complete, Kim sends announcement e-mail approving release for production.
DEVELOPMENT
Development consists of creating potentially releasable changes during a period of No Change Control and a period of Light Change Control.
STEAM
MORE than 60 days before target date
Prior to Water (feature-level change control), there is great freedom to propose changes because resources have not been allocated toward integrating and testing the proposed changes. We allocate these resources with release contracts.
WATER
60-30 days before target date
When Steam transitions to Water, changes requiring reallocation of integration, test, or downstream resources (i.e. requiring a new release contract) will require approval by module maintainers and Release Management before being accepted. Minor changes can still be added without approval for another 15 days. Changes requiring great coordination to deliver like string changes and UI changes will be deferred if possible.
INTEGRATION
- Create release contracts for each desired change. See previous examples.
- Combine potentially releasable changes and fix any resulting bugs.
Medium Change Control
All translation packages must be final by this time.
On or before this date Module maintainers propose a set of bug fixes to get into the testing branch. They usually do so by releasing a new version of their module and informing the release team about the changes it contains and the steps necessary to test those. The release team will make sure that
the relevant QA is executed and either approve the changes or ask for fixes/improvements. As soon as the changes are approved they are added to the testing build. After this date no changes are allowed in to the code without the approval of the module maintainer and the Release Triage team.
RELEASE
Execute the Software ECO process to deliver the release.