:''Carol'' -- coder who diagnoses, designs, codes, and reviews code.
:''Carol'' -- coder who diagnoses, designs, codes, and reviews code.
:''Mark'' -- module maintainer (packager) aggregates code and pushes it into build streams (i.e. into [[Developer/Fedora|Fedora]] or [[Build system#Instructions for use|Joyride]]).
:''Mark'' -- module maintainer (packager) aggregates code and pushes it into build streams (i.e. into [[Developer/Fedora|Fedora]] or [[Build system#Instructions for use|Joyride]]).
:''Rob'' -- [[release team]] member who approves requests to modify a stable build stream.
:''Bill'' -- [[build team]] member
:''Qilei'' -- [[QA team]] member


=== Story ===
=== Story ===
Line 82: Line 85:
#* If the test fails, then the tester may remand the issue to an earlier state and owner; otherwise, the tester should advance the ticket to the next state (see below).
#* If the test fails, then the tester may remand the issue to an earlier state and owner; otherwise, the tester should advance the ticket to the next state (see below).
# ''During change control'', changes must pass through three additional steps:
# ''During change control'', changes must pass through three additional steps:
## Changes cannot be committed to the stable build stream without meeting [[#Requirements for Approval|basic requirements]]. Tickets in the '''approval for release''' state will be regularly examined by the [[Release team]].
## Changes cannot be committed to the stable build stream without meeting [[#Requirements for Approval|basic requirements]]. Rob will regularly review tickets in the '''approval for release''' state.
## Approved changes will be sent to the build team in the '''add to release''' state.
## Approved changes will be sent to the build team in the '''add to release''' state.
## Once added, the ticket will be put in the '''test in release''' state for further testing.
## Once Bill updates the stable build stream, he will place the ticket in the '''test in release''' state for further testing.
# ''Occasionally'', an issue require test facilities beyond those available to ordinary developers and testers or are so important that they require additional [[systematic testing]]. Such issues should pass through the '''qa signoff''' state.
# ''Occasionally'', an issue require test facilities beyond those available to ordinary developers and testers or are so important that they require additional [[systematic testing]]. Such issues should pass through the '''qa signoff''' state where Qilei will examine them.
# Eventually, ''user-facing issues'' will need to be documented in the [[Release Notes]]. This occurs in the '''finalize''' state.
# Eventually, Rob will document tickets which reach the '''finalize''' state in the [[Release Notes]].
# Ultimately, tickets which require ''no further action'' can be ''closed''.
# Ultimately, tickets which require ''no further action'' can be ''closed''.
#* Rob is responsible for closing user-facing issues which result in changes to the build or work-arounds.
#* Other issues can be closed by anyone when they cease to be relevant to the release process.


[[Category:Trac]]
[[Category:Trac]]

Revision as of 23:44, 3 September 2008

Workflow States

Here is an approximate common path, subject to circumstances, followed by a toy user story.

A Trac ticket's position in the workflow is recorded in its Action Needed field. This field can contain the following values:

 (everyone should):
 reproduce       --  first we need to know how to reproduce your issue
 diagnose        --  then its root cause needs to be diagnosed
 design          --  at which time we can design...
 code            --  and code a fix.
 review          --  to ship the fix, we need to review it,
 testcase        --  write a test case for it,  
 
 (module maintainers should):  
 package         --  and package it up as an RPM, an activity, etc.
 add to build    --  then package needs to be added to a development build
 
 (everyone should):
 test in build   --  and the packaging needs to be tested.
   
 (during change control):
 approve for release --  get approval to add the package to a stable build stream (stable builds only)
 add to release  --  approved changes need to be committed
 test in release --  and retested at least once...
 
 (everyone should):
 qa signoff      --  some developers will want QA to review their work... (optional)
 finalize        --  before being added to the release notes
 no action       --  and closed.


Approval for Release

We enter change-control near the end of each release (e.g. 8.2.0 release schedule). When we enter change control, the ticket workflow expands to include the 'approve for release', 'add to release', and 'test in release' actions.

In order to pass the 'approve for release' action, you are expected to provide:

packages
a complete list of the packages (in source: (E)NVR form, e.g. koji: rainbow-0.7.20.fc9) which must be included to effect your change.
changelog
a nice human-readable description of your change including citations of tickets that will need to be updated as it is processed.
testcases
checkable test cases in either the |TestCase| Sugar style, the Systematic testing style, or the Tinderbox style.
(optional) risk assessment
an explanation, if convenient, of what risks are incurred by accepting your change.


General Notes

  • After testing in a build, the developer tags the bug with the results, e.g.:
 joyride-2126:-    or   joyride-2126:+
 ( '-' means bad result, try again, whereas '+' means good result )
  • The purpose of the finalize state is for the release team to provide any user-facing documentation or to conclude that no documentation is necessary.
  • The workflow can be exited early by resolving a ticket as 'worksforme', 'invalid', etc.
  • At various times, someone (e.g. the developer or the release team) may need an answer to a question. In this event, the ticket's next action should be set to 'communicate'.
  • Finally, the other 'Action Needed' states can be used to describe ignorance about what sort of action is needed. The regular Trac triage process will be responsible for pushing these tickets along.


User Story

Characters

Alice -- generic (possibly minimally skilled) Trac user.
Terry -- ticket herder who watches incoming tickets and improves their quality.
Carol -- coder who diagnoses, designs, codes, and reviews code.
Mark -- module maintainer (packager) aggregates code and pushes it into build streams (i.e. into Fedora or Joyride).
Rob -- release team member who approves requests to modify a stable build stream.
Bill -- build team member
Qilei -- QA team member

Story

  1. Alice observed curious behavior while exploring the system. She records it in Trac but does not set the next action field.
  2. Terry decides Alice's reported behavior is significant but doesn't know how to reproduce it so he changes the next action to reproduce to indicate his need for instructions on how to reproduce the issue.
    • Terry might instead have closed Alice's ticket as invalid, worksforme, etc or have sent it on to a later state if Alice wrote a particularly good ticket.
    • If necessary, Terry would also fill in the Milestone, Component, Keywords, and CC fields to conform to our Trac conventions.
  3. Once Alice's behavior can be reproduced, it can be diagnose[d] by Carol (probably with help from Alice).
  4. Carol will eventually propose a design that she thinks will resolve the issue.
  5. Carol will code to her design and will seek review of her work. She will also write a testcase.
  6. When all is in order, Carol or Mark will package the changes and add them to a development build (in the add to build state).
  7. When built in Joyride, Carol or Mark will test in build.
    • If the test fails, then the tester may remand the issue to an earlier state and owner; otherwise, the tester should advance the ticket to the next state (see below).
  8. During change control, changes must pass through three additional steps:
    1. Changes cannot be committed to the stable build stream without meeting basic requirements. Rob will regularly review tickets in the approval for release state.
    2. Approved changes will be sent to the build team in the add to release state.
    3. Once Bill updates the stable build stream, he will place the ticket in the test in release state for further testing.
  9. Occasionally, an issue require test facilities beyond those available to ordinary developers and testers or are so important that they require additional systematic testing. Such issues should pass through the qa signoff state where Qilei will examine them.
  10. Eventually, Rob will document tickets which reach the finalize state in the Release Notes.
  11. Ultimately, tickets which require no further action can be closed.
    • Rob is responsible for closing user-facing issues which result in changes to the build or work-arounds.
    • Other issues can be closed by anyone when they cease to be relevant to the release process.